![]() Gray Gantt bars represent the original Baseline schedule of each task Blue Gantt bars represent the current schedule of non-Critical tasks (tasks that can slip at least some without impacting the final Finish date of the project)ģ. Red Gantt bars represent the current schedule of Critical tasks (tasks that cannot slip without impacting the final Finish date of the projectĢ. ![]() The Gantt Chart screen in the Tracking Gantt view displays three different colors of Gantt bars. On the other hand, if you are referring to the Gantt Chart view, you can see the information you want to see by applying the Tracking Gantt view. ![]() When you use the term "timeline" in your post, are you referring to the Timeline view or are you referring to the Gantt Chart view that shows the timeline of the project? If you are referring to the Timeline view, there is no way to customize this view to show the Baseline Start and Baseline Finish fields. ![]()